1. Project Title
Liquid-cooled Top-mounted 3kW + Air-cooled 1500W Solution for C&I BESS Project in Dubai, UAE
Customized cabinet air conditioning system using Cooltec’s 3kW liquid cooling and 1500W air cooling units.
2. Client Background
The client is one of the leading energy and storage companies in Dubai, UAE, specializing in the design and construction of commercial & industrial (C&I) energy storage systems, including utility-scale projects up to 5GW.
3. Project Requirements & Challenges
The client required a combination of top-mounted outdoor liquid cooling units and cabinet-type air-cooled units for their BESS containers.
Key challenges included:
-
Extreme environmental conditions: ambient temperatures up to 50°C, frequent dust storms, and remote installation sites.
-
Equipment must meet IP65 protection standards and ensure long-term, stable operation in harsh desert environments.
4. Our Solution
Cooltec provided a fully customized thermal management solution, including:
-
Cooltechx 3kW top-mounted liquid cooling units
-
1500W air-cooled cabinet air conditioners
-
High-efficiency compressors, anti-corrosion components, and remote monitoring modules for real-time operation and diagnostics.
All systems were engineered for extreme climate durability and high system availability.
5. Deployment & Implementation
-
Design & customization period: 30 days
-
Delivery & installation cycle: 7 days
-
On-site or remote support is provided by Cooltec’s engineering team.
6. Outcome & Value
Since deployment, the system has operated continuously and fault-free for over 3 months.
The client has expressed strong satisfaction and plans to place a follow-up order for 30 additional units.
Key Project Metrics
Specification | Details |
---|---|
Cooling Solution | 3kW Liquid Cooling (Top-Mounted) + 1500W Air-Cooled |
Target Application | C&I Battery Energy Storage (BESS) Cabinet |
Location | Dubai, United Arab Emirates |
Operating Conditions | Max Ambient Temp 50°C, IP65, Dust-Prone Zone |
Delivery Schedule | 37 days (30 days production + 7 days transit) |
Performance Duration | 90+ days of continuous operation, no faults |
Expansion Plan | 30 additional units confirmed for rollout |